![]() |
|
Operations
Ghana
Overview
Chirano
Introduction
Location
Ownership
Geology
Mineralisation
Development & Mining
Technical Reports
Animated Tour
Photo Gallery
Bolgatanga
Ahafo North
Bibiani North
Akyem
Enchi
Bole
Mauritania
|
CHIRANO GOLD MINE
Location The Chirano Mine is situated in southwestern Ghana, 100 kilometres southwest of Kumasi, which is Ghana's second largest city. The township of Bibiani, the site of an existing large gold mine, lies 15 kilometres north-northeast of the project area (37 kilometres by road). Access to the mine from the capital Accra is via a sealed highway to Kumasi and then sealed highway running southwest towards Bibiani and onwards to Sefwi-Bekwai. The final approach is either by a 22 kilometre gravel road from Tanoso Junction (15 kilometres south of Bibiani) or by a 13 kilometre gravel road whose junction is approximately 9 kilometres beyond Sefwi-Bekwai. The project area is dominated by steep terrain and dense vegetation interspersed with small agricultural plots of palm oil, cassava and cocoa. Ownership The Chirano Mine and the mining lease on which it is based are owned 100% by CGML, a Ghanaian subsidiary of Red Back. CGML is currently 100% owned by Red Back through its intermediate subsidiary, Red Back Mining (Ghana) Limited. On April 8, 2004, CGML was issued a mining lease (PL2/56) in respect of the Chirano Project valid for a period of 15 years. The Government of Ghana retains the right to back-in to a 10% carried interest in the Chirano Project under Section 8 of the Ghana Mining Act, which interest may be increased to 30% by negotiation and arbitration. This 10% interest would represent a portion of CGM's 100% interest. The mining lease is exclusive to CGML, and is not subject to any option or joint venture arrangement. No back-in rights are held by any party other than the Government of Ghana. A royalty is payable to the Government of Ghana equal to 3% of gross revenue. An additional royalty equal to 0.6% of gross revenue is payable in relation to minerals extracted from Ghana's productive forest reserves. Production from most of the Chirano Project is subject to this extra royalty. The Government of Ghana retains the right to take a 10% interest in the project under Section 8 of the Ghanaian Mining Act. Geology The Chirano Mine lies within the Proterozoic terrain of southwest Ghana. It occurs along the margin of the Sefwi Belt adjacent to the Kumasi Basin to the east. Both the Sefwi Belt and the Kumasi Basin comprise rocks of Birimian age, with the belt dominated by mafic volcanics and the basin typified by fine grained, deep water sediments. Both are intruded by granites. The belt margin is characterized by regional scale, reactivated thrust faults which juxtapose the sedimentary basin and volcanic belt terrains and are known in the Chirano area as the Bibiani shear zone since the Bibiani deposit (+5Moz historic production and current resources) is inferred to be located along the same structure 18 km to the northeast. The Chirano deposits are hosted by the Chirano shear zone, a splay off the Bibiani shear. At Chirano, a small, faulted sliver of younger Tarkwaian shallow water sediments (dominantly arkose) separates the two structures. The Chirano gold deposits are hosted by an elongate, altered tonalite intrusive, adjacent to or within 200m to the west of the Chirano shear. The deposits occur at regular intervals along a mineralised zone 9 kilometres long. The geometry and shape of the deposits range from tabular (Obra), or pipe-like (Tano), to multiple parallel lodes (Paboase). The mineralised zone thickness ranges from a few metres to over 70 metres. Most deposits dip very steeply towards the west or southwest, and also plunge very steeply. Generally, the tenor of the gold mineralisation correlates with the intensity of alteration, veining and brecciation. Development & Mining The current mine plan calls for the exploitation of eleven gold deposits spread along a strike length of approximately nine kilometers by both open pit and underground mining methods. The nameplate capacity of the Chirano mill is 2.1 Mt per annum.The Chirano Plant is currently undergoing an expansion to a nominal throughput capacity of 3.5 mtpa. The operation utilizes selective mining techniques to separate ore and waste and is carried out by a mining contractor. The mining fleet is a combination of 250 tonne hydraulic excavators with 14 cubic metre buckets loading 100 tonne trucks. Drilling and blasting is required for all primary material and the majority of oxide material. The new treatment plant flowsheet is based on tertiary stage crushing, three ball mills, pre-leach thickening, a single stage of leaching and an eight stage CIL circuit. Gold is recovered by an elution circuit with electrowinning of the gold onto stainless steel cathodes. The gold will be removed from the cathodes with high pressure water sprays and smelted to a final bullion product. The plant commissioning is expected to commence during the first quarter of 2009. Akwaaba Deeps Development Akwaaba Deeps will be mined using a Sub-level Caving ("SLC") mining method. The bulk tonnage mining study estimates approximately 8.8 million tonnes will be mined at a grade of 3.7 g/t containing 1.0 million ounces. The capital cost to construct Akwaaba Deeps is estimated to be US $67m inclusive of owners costs and contingency. Life of the mine operating costs to deliver underground ore to Chirano mill have been estimated to be approximately $25 per tonne (inclusive of contingency). The underground development of Akwaaba Deeps is well underway. In order to support the new Akwaaba Deeps underground development, the Company is expanding the Chirano processing facility to a nominal throughput of 3.5 mtpa. In addition to increasing capacity, the expansion also addresses the rock hardness issue identified in 2007. A new crushing facility will reduce ore to 80% passing 12.5mm, optimizing milling efficiencies with the addition of a third mill and the conversion of the SAG mill to a ball mill. Chirano Resources The revised open pit and underground resources at Chirano as at December 31, 2009 are as follows:
The independent Resource estimate reported was undertaken by Nic Johnson (Member of the Australian Institute of Geoscientists) of Hellman and Schofield Pty Ltd with more than five years experience in the use of geostatistics for estimation of recoverable resources in gold deposits. For the purpose of reporting under National Instrument 43-101 Mr. Johnson is regarded as a Qualified Person. Chirano Reserves The Company’s consultants, AMC Consultants, have re-estimated Mineral Reserves for the Chirano mine, which are reported below as at 31 December 2009:
Open Pits Akwaaba Paboase The independent Surface Mineral Reserve estimate reported was undertaken under the supervision of Bruce Gregory (Member of the Australasian Institute of Mining and Metallurgy), Principal Mining Engineer of AMC Consultants Pty Ltd with more than five years experience in Ore Reserve estimation. For the purpose of reporting under National Instrument 43-101 Bruce Gregory is regarded as a Qualified Person. The independent Akwaaba Deeps Undergound Mineral Reserve estimate reported was undertaken by Tony Silveira (Member of the Australasian Institute of Mining and Metallurgy), Senior Mining Engineer of AMC Consultants Pty Ltd with more than five years experience in Ore Reserve estimation. For the purpose of reporting under National Instrument 43-101 Tony Silveira is regarded as a Qualified Person The independent Underground Ore Reserve estimate reported herein was undertaken by Herbert Smith B.Sc., P.Eng. (Member of the Association of Professional Engineers and Geoscientists of B.C.) of AMC Mining Consultants (Canada) Ltd with more than five years experience in Ore Reserve estimation for the purpose of reporting under National Instrument 43-101 Mr Smith is regarded as a Qualified Person. Animated Tour
Photo Gallery Akwaaba Deeps December 2008 Chirano Site (Feburary 2008) Chirano Site (October 2006) Chirano Site Visit (April 2006) First Gold Bar
Progress as of September, 2005
Progress as of August, 2005
Progress as of June, 2005
Early Stage Development Previous. All pages. Next. Page 1. Page 2 Previous. All pages. Next. Page 1. Page 2 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Home Operations Investors News Corporate Responsibility QwikReport Contact | |